Is it necessary to wait before performing a strength test on the molded specimens?

Yes, a waiting period is needed

A waiting period is necessary before performing a strength test on molded specimens primarily to ensure accurate and reliable results. This waiting period allows the concrete to cure and gain strength adequately. Concrete undergoes a hydration process, where water and cement react over time. Testing too early, such as immediately after casting, could yield misleading results, as the concrete may not have achieved its intended strength due to insufficient curing.

Typically, for compressive strength tests, concrete specimens should be allowed to cure for a minimum of 24 hours in a controlled environment to ensure that any potential initial setting effects have stabilized and that the concrete has had time to bond and harden effectively. This practice is standardized in many testing protocols and is essential for ensuring the integrity and validity of strength testing results.

Get further explanation with Examzify DeepDiveBeta

No, tests can be done immediately

Only for specific types of concrete

Only if the concrete is warm